Oyster Creek Station

Oyster Creek Decommissioning

Oyster Creek Decommissioning

The Oyster Creek Generating Station permanently ceased operation Sept. 17, 2018, leaving a 49-year legacy of safe, reliable, carbon-free electricity generation and service to the community.  The site has now entered a new era—the safe decommissioning and dismantlement of its components, systems and buildings.

In July of 2019, Oyster Creek was purchased by Holtec International in a deal that allowed the site to enter immediate decommissioning. The move enables the decommissioning and site release decades sooner than previously anticipated. The shorter decommissioning period benefits the community by allowing the site to be repurposed.


Our Goals for Decommissioning Oyster Creek

 
Achieving excellence in the health and safety of personnel
 
Protecting the environment now and for future generations
 
Ensuring a safe, respectful and equal opportunity workplace
 
Demanding the highest level of individual and corporate integrity
 
Continually improving upon our robust quality assurance program

 
Employing financially sustainable business practices
 
Maintaining transparent and ongoing communication with stakeholders
 
Fulfilling our promise to be a trusted steward of legacy nuclear materials

Decommissioning Nuclear Power Plants

Decommissioning is the process by which nuclear power plants are safely retired from service. The progression involves decontaminating the facility to reduce residual radioactivity, dismantling the structures, removing contaminated materials to appropriate disposal facilities and releasing the property for other uses. The owner remains accountable to the NRC until decommissioning has been completed and the agency has terminated its license.


Here’s a brief look at what will occur at Oyster Creek:

  1. The reactor was powered down on Sept. 17, 2018. This removed 650 megawatts of electricity from the regional grid.
  2. Oyster Creek’s fuel has been removed from the reactor vessel and placed in the spent fuel pool to cool.
  3. Following a short cooling time, nuclear fuel will be placed in robust, heavily shielded storage containers and transported to the Independent Spent Fuel Storage Installation (ISFSI) Facility, where it is guarded around the clock.
  4. Radioactive equipment and components are dismantled per an approved decommissioning plan.
  5. Contaminated components are dismantled, securely packaged and transported to a licensed off-site facility.
  6. The site is inspected by state and federal agencies to ensure the property has been returned to conditions outlined in the decommissioning plans. Both the State and Federal agencies will continue to monitor the site.

Our Decommissioning Team:

After Oyster Creek ceased operations many of the operations employees transferred into a decommissioning organization. Throughout the decommissioning lifecycle many of the same employees will assist in the safe dismantlement of Oyster Creek. Here’s a look at what we will be doing.

Protecting the facility and the public:

A security force will safeguard the facility until all nuclear fuel has been removed from the site.

Engineers, technicians & craftworkers:

A highly qualified, skilled staff of experts will oversee and conduct the entire dismantlement process.

Environmental Scientists:

Using company employees and contracted experts, we will continue a strong environmental monitoring program through decommissioning.

Emergency Responders:

Teams of qualified employees, both on and off-site, will be on-call all day, every day to work to protect the plant and the public in an unlikely emergency situation.


Overview of Decommissioning Process

  • To decommission a nuclear power plant, the licensee must submit A Post‐Shutdown Decommissioning Activities Report (PSDAR) to the NRC. This report provides a description of the planned decommissioning activities, a schedule for accomplishing them, and an estimate of the expected costs.
  • The licensee has to reduce the residual radioactivity to levels that permit release of the property and termination of the facility’s operating license. The site must be decommissioned within 60 years of the plant ceasing operations.
  • The decommissioning process involves removing the used nuclear fuel from the reactor; dismantling systems or components containing radioactive products (e.g. the reactor vessel); and cleaning up or dismantling contaminated materials from the facility.
  • Contaminated materials can be disposed of in two ways: decontaminated on site or removed and shipped to a waste processing, storage or disposal facility.

Decommissioning Options

(Companies can choose one or both options)

  • SAFSTOR (Safe Storage) ‐ Plant is kept intact, all fuel is placed in spent fuel pool or dry storage casks and time is used as a decontaminating agent. Plant is then dismantled similar to DECON once radioactivity has decayed to lower levels.
  • DECON (Decontamination) ‐ Contaminated equipment and materials are removed (used nuclear fuel rods and equipment account for over 99 percent of the plant’s radioactivity). Plant is then dismantled ‐ this phase can take five years or longer.

Terminating the NRC License, Releasing the Site

As the DECON phase nears completion, the company must submit a license termination plan to the NRC. This needs to occur within two years of the proposed license termination date. After the NRC receives the license termination plan, affected states, local communities and tribes may submit comments on the plan at a public meeting near the facility. The public also has the opportunity to request an adjudicatory hearing. Members of the public may observe any meeting the NRC holds with the company, unless the discussion involves proprietary, sensitive, safeguarded or classified information.

Once public concerns are addressed, the NRC will terminate the license if all work has followed the approved license termination plan and the final radiation survey shows that the site is suitable for release. Most plans envision releasing the site to the public for unrestricted use, meaning any residual radiation would be below NRC’s limits of 25 millirem per year. This completes the decommissioning process. 


FAQs→


Contact Us

Holtec Decommissioning International

HDI is Licensed Operator for Oyster Creek

Holtec Decommissioning International (HDI) is a wholly owned subsidiary of Holtec International headquartered at the Krishna P. Singh Technology Campus, Camden, NJ. HDI functions as the licensed operator for Holtec owned nuclear power plants. HDI provides the licensee oversight of Comprehensive Decommissioning International (CDI), Holtec and SNC-Lavalin’s jointly owned decommissioning general contractor.